Calverton Tip Drainage Channels

Client: Walters UK for the Coal Authority


Background: Colliery shale and sandy soils have one thing in common; both are highly susceptible to erosion by flowing water. Both soil types are present at Calverton Colliery Tip Restoration Project near Nottingham. Over 1km of Drainage ditch had been severely eroded before any vegetation had chance to establish.

 

Initial options included rock riprap lining, but the client and consultants preferred a more natural vegetated option.

 

Analysis of the channels revealed that even if vegetation could be established the un-cohesive sandy soils would not remain stable as the predicted flow velocities would be too extreme for a grass cover alone to withstand.

 

Design: Salix were approached to provide an initial design analysis and review of methods, which would enable the establishment of a vegetative cover both in the short and long term. Using the “shear stress” approach the level of erosive force was first assessed using the North American Green ECMDS software (Erosion Control Materials Design Software). This information was then compared to known design values for unreinforced and reinforced vegetative linings on sandy soil types.

 

Critically, the erosion protection needed to be able to withstand potentially high flow velocities (3.5m/s) immediately after installation and prior to vegetation becoming established. In an unvegetated state open three-dimensional erosion control mats fail at very low velocities (0.5m/s), as they only actually cover 5-10% of the soil surface. However, the vegetative stem and root reinforcement provided by a three dimensional mat was needed to reinforce the vegetation to enable the grass to withstand the higher velocity flow events.

 

The only product that would meet both the short term erosion control of the bare recently seeded soil whilst also giving three-dimensional reinforcement to the vegetation once established was North American Green’s (http://www.nagreen.com/) V-Max range of products. The ECMDS analysis showed that the C350 Composite Turf Reinforcement Mat (C-TRM) would provide the short term erosion control function and also reinforce the vegetation to withstand the storm flow events.

 

The eroded channels were re-profiled and shaped in March 2004 and seeded and protected with the C350 within a two-week period. The seed and fertilizer were protected from washout by flows in the channel from day one. An added benefit was the rate at which vegetation began to establish due to the mulching effect of the coir fibre composite layer in the 3-D net of the C350.

 

Results: The channels were tested early on after completion with numerous storm events occurring in the first few months. The high level of erosion control performance provided by the C350 prevented any erosion of fines or loss of seed. Vegetation is well on its way with 60 – 80% cover in the first year and the project is deemed a success by all those involved.

 


Materials used: North American Green C350

 

Calverton Colliery Tip, Nottingham

Calverton Colliery Tip, Nottingham

Laying of NAG C350 at Calverton Tip
Laying of NAG C350 at Calverton Tip

North American Green C350 at Calverton Colliery Tip, Nottingham.
North American Green C350 at

Calverton Colliery Tip, Nottingham

 

Arial view at Calverton Colliery Tip
Arial view at Calverton Colliery Tip

 

Calverton Colliery Tip before (above left), during (above right) and after (below).

Calverton Colliery Tip before (above left), during (above right) and after (below).
Calverton Colliery Tip before (above left), during (above right) and

after (below)

 
Calverton Colliery Tip before (above left), during (above right) and after (below).

 


Salix footer image